What concrete actually costs
Ready-mix is quoted per cubic yard, but the number on your invoice is rarely the number on the price list. Here is what moves it, and what catches people out.
The per-yard number, and why it is a range
Ready-mix concrete commonly runs $140 to $190 per cubic yard delivered in 2026, and a national average is close to useless because the spread within a single metro can be $30. The price is mostly haulage: concrete is heavy, it has a working life of about ninety minutes, and a plant forty minutes from your site costs more to serve you from than one ten minutes away.
The mix matters next. A 3000 PSI mix is the cheap end and fine for a shed floor; 3500 to 4000 PSI is standard for driveways and anything that freezes. Fibre, accelerator for a cold pour, retarder for a hot one, and air entrainment for freeze-thaw regions each add a few dollars a yard. None of them are optional in the conditions that require them.
The only figure worth quoting from is your own supplier's, for your own mix, this month. Put it in your price book once and every estimate uses it — that is the whole reason a price book exists, and what the paid plan is for.
The fees that arrive after you have quoted
Short-load fee. Under about 3 yards most suppliers add $60 to $150, because they are sending a full truck either way. This is the one that most often eats a small job's margin, because it appears on the invoice after the client has accepted a price.
Standby or demurrage. You typically get somewhere between five and eight minutes of unloading per yard included. Past that it is often $2 to $4 a minute. A crew that is not ready when the truck arrives is paying for the privilege.
Saturday, after-hours and winter surcharges. Weekend delivery is commonly $75 to $150. Hot-water mix in winter and ice in high summer both carry a charge.
Environmental and washout fees. Small, fixed, and on almost every invoice — $15 to $40. Worth knowing they exist rather than absorbing them silently on every job of the year.
The short-load fee lands hardest on the small pours, which is most of the work a lot of crews do. A flight of steps is usually a yard and a bit and a set of deck piers is often under one — work out exactly where you land with the steps calculator or the Sonotube calculator before you accept the fee, because combining the two into a single pour frequently clears the threshold on its own.
Per square foot, which is how clients think
Homeowners ask what a driveway costs per square foot, and a bare concrete number will not answer it, because the concrete is usually only a third of the job. Excavation, base stone, forming, steel, placing, finishing, control joints and cleanup are the rest.
As a broad guide, plain finished flatwork often lands somewhere around $8 to $14 per square foot installed, with stamped or coloured work substantially higher. Your own numbers will differ, and they should — the point of pricing from your own costs rather than a published average is that you are not quoting somebody else's market.
Work out the concrete first, then add base, steel and labour as separate lines. A quote that shows the client what they are paying for wins more often than one flat figure, because it survives being compared against two other bids.
Do not price off a national average
Every number on this page is a range, and that is deliberate. The most expensive mistake in concrete pricing is treating a figure from an article as your cost — including this article. Ring your supplier, get their yard price for the mix you actually use, ask what their short-load threshold and fee are, and write both down.
Then price every job off those numbers rather than off memory. Contractors who quote from memory drift low over time, because the number they remember is the one from before the last price rise.
Work out your own numbers
Send it as a quote, not a number
BidPour turns the quantities into a priced, branded estimate your client accepts from their phone — your material costs, your markup, your logo.
- First quote free, no card, no account
- See the moment they open it
Common questions
How much is a yard of concrete in 2026?
Commonly $140 to $190 delivered, depending on region, mix strength, admixtures and haul distance from the plant. Short-load fees, standby time and weekend surcharges sit on top of the yard price.
How much does a concrete driveway cost?
Plain finished flatwork often lands around $8 to $14 per square foot installed, so a 24 × 36 driveway is broadly $7,000 to $12,000. Concrete itself is usually about a third of that; excavation, base, steel, forming and finishing are the rest.
Why did my concrete invoice come in higher than the quote?
Almost always short-load fees, standby time past the included unloading minutes, or a surcharge for weekend or cold-weather delivery. Ask your supplier for their full fee schedule once and you can price every one of them in.
Is concrete cheaper by the truckload?
Per yard, yes — a full load avoids the short-load penalty and spreads the delivery over more material. It is why combining a footing and slab pour into one order is often cheaper than two separate deliveries.